SRTS Phase V (Sidewalks) (Current)

Safe Routes to School (SRTS) Phase V is a continuation of the city's long-term goal of extending sidewalks under the federal SRTS program (now Transportation Alternative Program (TAP)).  This project is projected to cost approximately $323.438 with ARDoT paying $256,697 and the city paying the remaining $66,741.

SRTS V will continue the sidewalk from Moon Rd Ext to Wilson Loop

September 2026 Update:  Waiting of ARDoT to release the project for bids.  All ROWs have been obtained.